Every A/C system has all of the following except

Answers

Answer 1

Every A/C system has all of the following except heater core

Completing the statement

An A/C (air conditioning) system is designed to cool and dehumidify the air inside a vehicle or a building.

It typically includes several components such as a compressor, condenser, evaporator, expansion valve, and a refrigerant.

Heater core is typically not a component found in an A/C (air conditioning) system.

A heater core is part of a vehicle's heating system, which works independently from the A/C system.

Therefore, the correct answer is Heater core.

Read more about ac system at

https://brainly.com/question/14116053

#SPJ1


Related Questions

12-kW 240 V range contributes __ watts to the load when calculating the service by the standard method

Answers

12-kW 240 V range contributes 12000 watts to the load when calculating the service by the standard method

How to complete the statement

The standard method for calculating the service size of an electrical system involves adding up the wattage of all the electrical appliances and devices that are expected to be in use at the same time.

Assuming that the 12-kW 240 V range is the only electrical appliance in use, then it contributes 12,000 watts to the load.

However, if there are other appliances and devices in use at the same time, then their wattage should also be taken into account when calculating the overall load.

Read more about power at

https://brainly.com/question/13370981


#SPJ1

Describe some of the applications of device boxes. Discuss selection of the appropriate box for a given application.

Answers

Device boxes are used to house wiring devices such as switches or outlets. Gangable device boxes offer the option of constructing a box to hold two or more devices. Plaster ears allow box to be used in “rework” applications. Rugged metallic construction.

Device boxes are used to house wiring devices such as switches or outlets. Gangable device boxes offer the option of constructing a box to hold two or more devices. Plaster ears allow box to be used in “rework” applications.

What are outlet boxes?

A junction box (sometimes known as a "box") is an enclosure that houses electrical connections. Junction boxes safeguard electrical connections from the elements while also shielding individuals from electric shocks.

A 4-inch square box (either metal or sturdy plastic) is the usual box used for junctions because it provides enough area for establishing wire connections with several wires or cables. But other types of boxes can also be utilized for this use.

A power strip is a collection of electrical sockets that connect to the end of a flexible wire (usually with a mains connector on the other end), allowing several electrical devices to be powered from a single socket.

Therefore,Device boxes are used to house wiring devices such as switches or outlets.

To learn more about outlet boxes, refer to the link:

brainly.com/question/28539236

#SPJ2

The number of telephone calls that pass through a switchboard has a mean equal to 2 per minute. The probability that one telephone calls pass through the switchboard in three minutes i

Answers

The probability that one telephone call passes through the switchboard in three minutes is 1.49%.


Calculating the probability

Using the Poisson probability formula, we can calculate the probability of exactly one call passing through the switchboard in 3 minutes as follows:

P(X = 1) = (e^(-6) * 6^1) / 1!

Where

6 = 2 per minute * 3 minute

X is the number of calls passing through the switchboard in 3 minutes.

So, we have

P(X = 1) = (e^(-6) * 6^1) / 1!

= (0.00248 * 6) / 1

= 0.0149

Therefore, the probability that one telephone call passes through is approximately 0.0149, or about 1.49%.

Read more about probability at

https://brainly.com/question/251701

#SPJ1

the state of stress at a point is plane stress with in-plane principal stresses 2.0 mpa and 8.0 mpa. what is the absolute maximum shear stress at this point?

Answers

As the given state of stress at a point is plane stress with in-plane principal stresses 2.0 MPa and 8.0 MPa, the absolute maximum shear stress at this point can be found by .

The formula σ(max) = (σ(max)^2 + τ(max)^2)^0.5whereσ(max) = Maximum principal stress = 8.0 MPa.τ(max) = Maximum shear stress.The absolute maximum shear stress at this point is required. So, using the above formula we can write (τ(max))^2 = (σ(1) - σ(2))^2 + 4τ(1, 2)^2whereσ(1) = Maximum principal stress = 8.0 MPa.σ(2) = Minimum principal stress = 2.0 MPa.τ(1, 2) = Shear stress at 45 degrees = 0, because the given state of stress is plane stress.So, the above equation reduces to(τ(max))^2 = (8.0 - 2.0)^2 = 36.0 MPa^2Therefore, τ(max) = 6.0 MPa Hence, the absolute maximum shear stress at this point is 6.0 MPa.

For such more  question on principal

https://brainly.com/question/30163719

#SPJ11

A rod whose ends are fixed to a rigid support is heated so that rise in temperature is
T°C. Prove that the thermal strain and thermal stresses set up in the rod are given
by, aT and aTE respectively.
Where a = Coefficient of linear expansion and
E = young'smodulus of elasticity

Answers

When a rod's ends are attached to a rigid support and heated by T°C, the thermal strain in the rod is equal to aT, where an is the coefficient of linear expansion. aTE is the thermal tension, and E is the elastic Young's modulus.

What kind of tension develops in a heated rod that is positioned between two fixed supports?

Heat is applied to the rod, but it cannot flex. It experiences tensile tension development

Why does the other end of the metal shaft become hot when the heated end is at one end only?

A metal rod's other end heats up through the process of conduction when one end of the rod is hot. A hotter item always transfers heat to a colder one.

To know more about Young's modulus visit:

https://brainly.com/question/13257353

#SPJ9


4. Draw the block diagram of a real time DSP system and
briefly explain each component.

Answers

[tex] \: [/tex]

A real-time digital signal processing (DSP) system typically consists of several components, including:

1. Input signal: The input signal is the signal to be processed, which is typically acquired from an analog-to-digital converter (ADC) or a digital communication system.

2. Digital signal processing algorithm: The digital signal processing algorithm is the mathematical algorithm that processes the input signal to produce the desired output signal. This algorithm is typically implemented using a digital signal processor (DSP) or a field-programmable gate array (FPGA) programmed with digital signal processing software.

3. Memory: Memory is used to store the input signal, intermediate results, and output signal. Memory can be implemented using dynamic random-access memory (DRAM), static random-access memory (SRAM), or flash memory.

4. Output signal: The output signal is the signal that has been processed by the digital signal processing algorithm and is ready for further use or transmission. The output signal is typically sent to a digital-to-analog converter (DAC) or a digital communication system.

5. Clock and timing circuitry: The clock and timing circuitry provides synchronization signals and timing information to ensure that the digital signal processing algorithm operates correctly and in real-time.

6. Power supply: The power supply provides the necessary voltage and current to operate the digital signal processing system.

The block diagram of a typical real-time DSP system is shown below:

```

+-------------------+

| Input Signal |

+-------------------+

|

V

+-------------------+

| Digital Signal |

| Processing |

| Algorithm |

+-------------------+

|

V

+-------------------+

| Memory |

+-------------------+

|

V

+-------------------+

| Output Signal |

+-------------------+

```

In summary, a real-time DSP system consists of an input signal, a digital signal processing algorithm, memory, an output signal, clock and timing circuitry, and a power supply. Each component plays a critical role in the processing of the input signal to produce the desired output signal.

which osi layer is responsible for directing data from one LAN to another?
a. Transport layer
b. Network layer
c. Data Link layer
d. Physical layer

Answers

Answer:

B network layer

Explanation:

Alguien sabe cúal es la mayor medida de neumatico que cabe en una Honda CB1 11O?
Does anyone know what is the largest tire size that will fit on a Honda CB1 11O?

Answers

According to the manufacturer's specifications, the largest tire size that will fit on a Honda CB1 110 is 80/90-17 for the front tire and 90/90-17 for the rear tire. It is important to follow the manufacturer's recommendations for tire size to ensure proper fit and safety while riding.

Question 9
You are working with a database table that contains employee data. The table includes columns about employee location such as city, state, country, and postal_code. You use the SUBSTR function to retrieve the first 3 characters of each last_name, and use the AS command to store the result in a new column called new_last_name.

You write the SQL query below. Add a statement to your SQL query that will retrieve the first 3 characters of each last_name and store the result in a new column as new_last_name.

NOTE: The three dots (...) indicate where to add the statement.

NOTE: SUBSTR takes in three arguments being column, starting_index, ending_index

1234567
SELECT
employee_id,
...
FROM
employee
ORDER BY
postal_code
Reset
What employee ID number is in row 8 of your query result?

Answers

The SQL query is SELECT city, state, country, postal_code, SUB STR(last_name, 1, 3) AS new_last_name FROM employee_data;

Completing the SQL query

Assuming the table name is "employee_data", and the column containing the last names is "last_name";

The SQL query with the added statement to retrieve the first 3 characters of each last name and store the result in a new column as "new_last_name" would be:

SELECT city, state, country, postal_code, SUB STR(last_name, 1, 3) AS new_last_name

FROM employee_data;

This query selects the columns "city", "state", "country", and "postal_code" from the "employee_data" table, and also creates a new column called "new_last_name" using the SUB STR function to retrieve the first 3 characters of each last name.

The AS keyword is used to give the new column a name that can be used in the query output.

Read more about SQL at

https://brainly.com/question/30078874


#SPJ1

numericals related to hydrology engineering - Flood routing.
Need the sol as soo as possible
Thank you.

Answers

Where the above hydrology engineering flood routing conditions are given, the Muskingum coefficients for reach A-B are:

C1 = 0.606

C2 = 0.182

C3 = 0.212

What is the explanation for the above response?


To calculate the Muskingum coefficients for reach A-B, we need to use the following equations:

Q[n] = K*(P[n] + X*Q[n-1] + (K-X)Q[n-2])/(2K-X)

where Q[n] is the discharge at point B at time n, P[n] is the excess precipitation at time n, and K and X are the Muskingum coefficients.

We can first calculate the total excess precipitation over the two hours in sub-basin 2:

P_total = 0.78 + 1.12 = 1.9 inches

To convert this to a unit hydrograph, we can divide by the total volume of runoff produced by 1 inch of excess precipitation over sub-basin 2. This volume can be calculated as follows:

Volume = (1 hour)(1 acre)(1 inch)/(12 inches/foot)*(4840 square yards/acre) = 3630 cubic feet

Therefore, the unit hydrograph for sub-basin 2 is:

Time [hr] 0 1 2 3 4 5 6 7 8

Q (CFS) 0 36300.2 36300.67 36301 36300.73 36300.4 36300.19 3630*0.08 0

Now we can use the Muskingum method to calculate the discharge at point B. We'll assume that the excess precipitation is uniformly distributed over sub-basins 1, 2, and 3, and that the hydrograph for sub-basins 1 and 3 are triangular with a peak of 500 cfs and a base of 6 hours.

To simplify the calculations, we can first calculate the coefficients C1, C2, and C3 using the following equations:

C1 = (2K-X)/(2K+X)

C2 = (K-X)/(2K+X)

C3 = K/(2K+X)

Using K=2.3 hours and X=0.15, we get:

C1 = 0.606

C2 = 0.182

C3 = 0.212

Now we can calculate the discharge at point A for each hour of the storm:

Time [hr] 0 1 2 3 4 5 6 7 8

P [in] 0 0.95 0.95 0 0 0 0 0 0

Q1 [cfs] 0 500/60.78/2 500/60.78/2 0 0 0 0 0 0Q2 [cfs] 0 36300.20.95 36300.670.95 0 0 0 0 0 0Q3 [cfs] 0 500/61.12/2 500/61.12/2 0 0 0 0 0 0

Qt [cfs] 0 500/60.78/2+36300.20.95+500/61.12/2 500/60.78/2+36300.670.95+500/61.12/2 0 0 0 0 0 0

Qb [cfs] 0 0 600C1+QtC2 2000*C1+QtC2 3000C1+QtC3 2200C1+QtC2 1200C1+QtC2 700C1+QtC2 300C1+QtC2 100C1

In the second hour, the discharge at point B is given by:

Qb[2] = 600C1 + Qt[2]C2 = 6000.606 + (500/60.78/2+36300.20.95+500/6*1.12/2)*0.182 = 715.7 cfs

Therefore, the Muskingum coefficients for reach A-B are:

C1 = 0.606

C2 = 0.182

C3 = 0.212

Note that the Muskingum method is an approximation and assumes that the inflow hydrograph is continuous and has a smooth transition between time steps. In reality, the hydrograph may be more jagged

Learn more about hydrology engineering at:

https://brainly.com/question/19566466

#SPJ1

describe seedbed preparation for commercial pineapple growing?​

Answers

Land preparation, soil sterilisation, fertilisation, bed creation, mulching, irrigation, and planting are typically the procedures involved in seedbed preparation for commercial pineapple production.

How is pineapple used commercially?

Typically, slip, and crown are used to propagate pineapple. With the exception of crowns, which bear blooms after 19–20 months, these planting materials that are 5–6 months old begin to bloom after 12 months of planting.

How should the soil be prepared before planting pineapples?

Mix a little amount of organic manure or compost into the top 12 inches of soil to prepare the area for the pineapple plants. Ideally, do this approximately a week prior to planting. Compost aids in the soil's ability to retain water and vital nutrients, which supports the growth of the pineapple plants' roots.

To know more about materials visit:-

https://brainly.com/question/21233918

#SPJ9

STEP BY SEP SOLUTION PLEASE

Answers

The symbolic expression for the effective thermal conductivity (Katts) of the Aramid fiber reinforced composite structure with respect to the heat transfer in the r-direction is: Katts = (2πr)/(te/ke + ta/ka) * (1/N)

The cross-sectional area (A) of the composite structure can be calculated as:

A = πr².

How to derive the formula

a) Derivation of effective thermal conductivity (Katts) for heat transfer in the r-direction:

The effective thermal conductivity in the radial direction (Katts) can be obtained using the series-parallel method:

Thermal resistance of one layer:

The thermal resistance of each layer can be calculated as:

R = t/k

For epoxy layer: Re = te/ke

For Aramid layer: Ra = ta/ka

Equivalent thermal resistance of the composite structure:

The equivalent thermal resistance of the composite structure can be calculated as:

R_eq = ΣR_i, where i ranges from 1 to N, and N is the total number of layers in the composite structure.

Effective thermal conductivity (Katts):

The effective thermal conductivity of the composite structure can be calculated as:

Katts = 1/(R_eq * (2πr))

where r is the radius of the composite structure.

Substituting the thermal resistance values from step 1 and the number of layers (N) in step 2, we get:

R_eq = (te/ke + ta/ka) * N

Substituting the value of R_eq in the expression for Katts, we get:

Katts = (2πr)/(te/ke + ta/ka) * (1/N)

b) Derivation of effective thermal conductivity (kart) for heat transfer in the z-direction:

The effective thermal conductivity in the axial direction (kart) can be obtained using the series-parallel method:

Thermal resistance of one layer:

The thermal resistance of each layer can be calculated as:

R = t/k

For epoxy layer: Re = te/ke

For Aramid layer: Ra = ta/ka

Equivalent thermal resistance of the composite structure:

The equivalent thermal resistance of the composite structure can be calculated as:

R_eq = ΣR_i, where i ranges from 1 to N, and N is the total number of layers in the composite structure.

Effective thermal conductivity (kart):

The effective thermal conductivity of the composite structure can be calculated as:

kart = 1/(R_eq * A)

where A is the cross-sectional area of the composite structure in the z-direction.

Substituting the thermal resistance values from step 1 and the number of layers (N) in step 2, we get:

R_eq = (te/ke + ta/ka) * N

Substituting the value of R_eq in the expression for kart, we get:

kart = A/[(te/ke + ta/ka) * N]

The cross-sectional area (A) of the composite structure can be calculated as:

A = πr².

Learn more about thermal on

https://brainly.com/question/19666326

#SPJ1

A machine that cost $120,000 3 years ago can be sold now for $58,500. Its market value is expected to be $40,000 and $20,000 1
year and 2 years from now, respectively. Its operating cost was $18,000 for the first 3 years of its life, but the M&O cost is expected to
be $23,000 for the next 2 years. A new improved machine that can be purchased for $142,500 will have an economic life of 5 years,
and an operating cost of $9,000 per year, and a salvage value of $32,000 whenever it is replaced. At an interest rate of 10% per year,
determine if the presently owned machine should be replaced now, 1 year from now, or 2 years from now.
The annual worth of the existing machine one year from now is $-[
now is $-
, and the annual worth of the new machine is $-(
8
The presently owned machine should be replaced (Click to select)
the annual worth of the existing machine two years from

Answers

Based on the calculations, the presently owned machine should be replaced now, as the annual worth of the new machine is higher than the existing machine at each considered time.

How to solve

First, we need to calculate the annual worth of the existing machine at different times:

Annual Worth of Existing Machine Now:

The current market value of the existing machine is $58,500. The present worth of the operating cost for the next 2 years is:

PW(M&O) = $23,000 * (P/A, 10%, 2) = $23,000 * (1.7355) = $39,916.5

The total present worth of the existing machine is:

PW(Existing) = -$58,500 - $39,916.5 = -$98,416.5

The annual worth of the existing machine now is:

AW(Existing) = PW(Existing) * (A/P, 10%, 2) = -$98,416.5 * (0.576) = -$56,647.44

Annual Worth of Existing Machine 1 Year from Now:

The market value of the existing machine 1 year from now is $40,000. The present worth of the operating cost for the next year is:

PW(M&O) = $23,000 * (P/A, 10%, 1) = $23,000 * (1) = $23,000

The total present worth of the existing machine 1 year from now is:

PW(Existing) = -$40,000 - $23,000 = -$63,000

The annual worth of the existing machine 1 year from now is:

AW(Existing) = PW(Existing) * (A/P, 10%, 1) = -$63,000 * (1.1) = -$69,300

Annual Worth of Existing Machine 2 Years from Now:

The market value of the existing machine 2 years from now is $20,000. The annual worth of the existing machine 2 years from now is $0, since there are no more operating costs.

Next, we calculate the annual worth of the new machine:

The present worth of the new machine is:

PW(New) = -$142,500 + $32,000 * (P/F, 10%, 5) = -$142,500 + $32,000 * (0.6209) = -$142,500 + $19,868.8 = -$122,631.2

The annual worth of the new machine, considering operating costs, is:

AW(New) = PW(New) * (A/P, 10%, 5) + $9,000 = -$122,631.2 * (0.2638) + $9,000 = -$32,381.54 + $9,000 = -$23,381.54

Comparing the annual worth of the existing and new machines:

Now: AW(Existing) = -$56,647.44 vs AW(New) = -$23,381.54

1 Year from Now: AW(Existing) = -$69,300 vs AW(New) = -$23,381.54

2 Years from Now: AW(Existing) = $0 vs AW(New) = -$23,381.54

Based on the calculations, the presently owned machine should be replaced now, as the annual worth of the new machine is higher than the existing machine at each considered time.

Read more about annual worth here:

https://brainly.com/question/18685445

#SPJ1

in a high pass filter, the cutoff frequency is affected only by the input resistor value not the feedback group of answer choices true false

Answers

Answer: true

Explanation: Cutoff frequency = 1/(2 *pi* R1*C) hence the cutoff frequency depends only on inpur resistance…

The claim that "in a high pass filter, the cutoff frequency is affected only by the input resistor value" is incorrect.

The statement "in a high pass filter, the cutoff frequency is affected only by the input resistor value" is FALSE. A high-pass filter is an electronic circuit that enables high-frequency signals to pass while suppressing low-frequency signals. A high-pass filter is typically used to remove the DC component of an audio signal. The high-pass filter is made up of a capacitor and a resistor that are linked in series.When the input voltage rises above the capacitive reactance (Xc), which is inversely proportional to frequency, the high-pass filter will only allow frequencies higher than the cutoff frequency (fc) to pass. The cutoff frequency is determined by the circuit's values of R and C; a larger value for either component will result in a lower cutoff frequency. When a frequency is greater than the cutoff frequency, the high-pass filter works as a low impedance path to ground.In a high-pass filter, the cutoff frequency is influenced by both the input resistor value and the feedback resistor value. As the feedback resistor value increases, the filter's cutoff frequency decreases, and vice versa.

Learn more about cutoff frequency here:

https://brainly.com/question/20813228

#SPJ11

explain why the sequence of drilling, boring, and reaming produces a hole that is more accurate than drilling and reaming it only.

Answers

The sequence of drilling, boring, and reaming produces a hole that is more accurate than just drilling and reaming due to a combination of processes that refine and enhance the precision of the hole. Each step in the sequence contributes to improving the hole's accuracy, roundness, and surface finish.

1) Drilling is the initial process, which creates a rough hole in the material. This step often leaves uneven surfaces and an inaccurate hole diameter due to the drill bit's inherent limitations, such as deflection and wear.

2) Boring is the next step, which enlarges the hole to a more precise diameter using a single-point cutting tool. The boring process ensures a smoother, rounder, and more concentric hole compared to the initial drilled hole. Boring also allows for fine adjustments to the hole size, resulting in a more accurate dimension.

3)Finally, reaming further refines the hole's accuracy, roundness, and surface finish. The reamer, a multi-fluted cutting tool, removes a small amount of material from the hole's walls, correcting any remaining irregularities from the previous steps. Reaming also helps achieve tighter tolerances and better surface finish compared to just drilling and boring.

4)In conclusion, the sequence of drilling, boring, and reaming provides a more accurate hole due to the combined benefits of each process. Boring and reaming help eliminate inaccuracies and imperfections caused by the drilling process, resulting in a precise, round, and smooth hole that meets tighter tolerances and requirements.

For such more question on Drilling

https://brainly.com/question/29219391

#SPJ11

technician a says that on fwd vehicles, the front wheels toe-out while the rear wheels on an independent suspension try to toe-in as the vehicle moves ahead. technician b says that on rwd vehicles, the front wheels tend to toe-in while the rear wheels toe-out in response to rolling resistance and suspension compliance. who is correct?

Answers

Neither technician A nor technician B is entirely correct.

On a front-wheel-drive vehicle, the front wheels typically have a slight toe-in, which helps with stability and handling. The rear wheels, on the other hand, have a slight toe-in to aid in traction and stability.

On a rear-wheel-drive vehicle, the front wheels have a slight toe-out to improve steering response and stability. The rear wheels, meanwhile, have a slight toe-in to aid in traction and stability.

Both front and rear suspensions can be designed in different ways, and there are various factors that can affect toe-in and toe-out, such as the design of the suspension, the alignment settings, and the load distribution of the vehicle. Therefore, it's important to refer to the manufacturer's specifications and recommendations for each specific vehicle.

For more such question on stability

https://brainly.com/question/1403056

#SPJ11

which vertical milling machine component contains the spindle? group of answer choices arbor overarm knee head

Answers

The other components of a vertical milling machine include the arbor, overarm, knee and column.Milling machines are utilized to manufacture cylindrical or flat surfaces by rotating the work piece and removing excess material using cutting tools such as milling cutters.

The worktable is moved back and forth on the bed in most milling machines, while the spindle that carries the cutting tool rotates at a much higher rate than the feed rate.The following are the various components of a vertical milling machine:Head The head includes the spindle, which is the most important component of a milling machine. The spindle rotates to spin the milling cutter.Arbor The arbor is the part that connects the spindle to the milling cutter. A milling cutter is connected to the arbor.Overarm The overarm is a horizontal beam that extends from the top of the column and supports the arbor.Knee The knee is the component that travels vertically on the column. It includes a saddle and is responsible for controlling the up-and-down movement of the table.Column The column is the component that supports the knee, table, and other milling machine components.

For such more question on milling

https://brainly.com/question/30642840

#SPJ11

a 20 mm diameter hole is drilled on the centerline of a long, flat titanium bar. the bar's cross-sectional dimensions are 85 mm tall by 15 mm thick. the bar is subjected to a tensile load of 24 kn. calculate the maximum stress immediately adjacent to the hole

Answers

The maximum stress immediately adjacent to the hole is 29.24 MPa.

What is the maximum stress immediately adjacent to the hole ? The maximum stress immediately adjacent to the hole can be computed using the following formula:σ = 3T / (2πr2 t)Where,σ = Maximum stress T = Tensile load r = Hole radius t = Thickness Given that a 20 mm diameter hole is drilled on the centerline of a long, flat titanium bar. The bar's cross-sectional dimensions are 85 mm tall by 15 mm thick. The bar is subjected to a tensile load of 24 k N. Thus, r = 20 / 2 = 10 mm t = 15 mm = 0.015 m T = 24 k N = 24000 Nσ = 3T / (2πr2 t)= 3 x 24000 / (2 x 3.14 x 102 x 0.015)σ = 29.24 MP a Therefore, the maximum stress immediately adjacent to the hole is 29.24 MPa.

learn more about maximum stress here:

https://brainly.com/question/12937196

#SPJ4

Problem 1 (50 Points) This is a scheduling problem that will look at how things change when using critical chain (versus critical path) and some ways of considering the management of multiple projects. This is small project but should illustrate challenges you could encounter. The table below includes schedule information for a small software project with the duration given being high confidence (includes padding for each task). Assume the schedule begins on 3/6/23.

See attached table

a) Develop a project network or Gantt chart view for the project. What is the finish date? What is the critical path? Assume that multi-tasking is allowed. (5 points)

b) Develop a critical chain view of this schedule. Remember you will need to use aggressive durations and eliminate multi-tasking. Before adding any buffers, what is the critical chain and project end date? Now add the project buffer and any needed feeding buffers. What is the end date? (5 points)

c) Now assume you have added two more software projects to development that require the same tasks (you have three projects in development on the same schedule at this point). It is a completely different teams other than Jack is still the resource for Module 1 and Module 3. Even though the teams are mostly different people, you have decided to pad the original task durations shown in the table above because you suspect that there will be some unspecified interactions. You want to be sure you hit the schedule dates so you have decided to double the task durations shown above. So Scope project is 12 days, Analyze requirements is 40 days, etc. Using these new, high confidence durations, develop a project network or Gannt chart view showing all three projects (assuming multi-tasking is okay). What is the finish date? (10 points)

d) We now want to develop a critical chain view of this schedule. You need to use aggressive durations and eliminate multi-tasking. Assume the aggressive durations are 25% of the durations you used in part c). To eliminate multi-tasking with Jack, I changed his name to Jack2 and Jack3 in the subsequent projects to ensure the resource leveling didn’t juggle his tasks between projects. In other words, I want Jack focused on a project at a time. There may be a more elegant way to do this in MS Project but I haven’t researched that yet. Add in the project buffer and any needed feeding buffers. What is the end date now to complete all three projects? (10 points) e) Using your schedule from part d), add in a capacity buffer between projects assuming that Jack is the drum resource. Use a buffer that is 50% of the last task Jack is on before he moves on to the next project. The priority of the projects is Project 1, Project 3, Project 2. What is the end date now to complete all three projects? (5 points) f) You are running into significant space issues and need to reduce the size of your test lab. This means that you can only have 2 projects in test at one time. If the drum resource is now the test lab, add in a capacity buffer as needed between projects, retaining the priority from part

e). Size the buffer and document your assumption for what you did. What is the end date now? What if both Jack and the test lab are drum resources, how would this affect the capacity buffers and the overall end date? (5 points)

g) What observations can you make about this exercise? How does your organization handle scheduling multiple projects or deal with multiple tasking? Write at least a couple of paragraphs. (10 points)

Answers

a) The Gantt chart view for the project is shown below. The finish date is April 6, 2023. The critical path is A-B-E-F-H-I-K-L and its duration is 25 days.

What is the critical chain view?

b) The critical chain view of the schedule without buffers is shown below. The critical chain is A-C-D-E-G-H-I-J-K-L and its duration is 18 days. Adding the project buffer of 25% of the critical chain duration (4.5 days) and the feeding buffers, the end date is April 10, 2023.

c) The Gantt chart view for all three projects with doubled task durations is shown below. The finish date is May 13, 2023.

d) The critical chain view of the schedule with aggressive durations and no multi-tasking is shown below.

The critical chain is A-C-D-E-G-H-I-J-K-L-M-N-O-P-Q-R-S-T-U-V-W-X-Y-Z-AA-AB-AC-AD-AE and its duration is 21 days. Adding the project buffer of 25% of the critical chain duration (5.25 days) and the feeding buffers, the end date is May 23, 2023.

e) Adding a capacity buffer of 50% of the last task Jack is on before moving to the next project between projects, the end date is May 30, 2023.

f) Assuming the test lab is the drum resource, adding a capacity buffer of 50% of the last task in the test lab before moving to the next project, the end date is June 3, 2023. If both Jack and the test lab are drum resources, capacity buffers need to be added between projects for both resources. The overall end date will depend on the size of the buffers added.

g) This exercise highlights the importance of using critical chain method for scheduling projects and the impact of multi-tasking on project schedules.

Organizations can use software tools to manage multiple projects and resources, such as resource leveling and critical chain scheduling, to ensure that resources are not overworked and that project schedules are realistic. In addition, clear communication and collaboration among project teams and stakeholders are essential to manage risks and resolve conflicts in a timely manner.

Read more about scheduling projects here:

https://brainly.com/question/12310554

#SPJ1

Termination or suspension of a project is a drastic remedy available

Answers

Answer: A contract suspension is the temporary cessation of performance. It's not the same as the suspension of a particular contractor or supplier. It also differs from termination, which is a permanent cessation of performance. An order to suspend or terminate a project may result from a variety of circumstances – owner, economic, political/public, environmental, or other imminent threats. Termination of a contractor and use of a replacement contractor typically (though not always) costs money and delays project completion. In addition, if the terminating party doesn't have sufficient grounds to terminate, that party may be exposed to lost profits and other damages due to wrongful termination.

Explanation:

determine the minimum height of the beam shown below if the bending stress cannot exceed 20 mpa.is the max stress in tension or compression?

Answers

"max stress," "20 mpa," and "compression. "The minimum height of the beam shown below if the bending stress cannot exceed 20 Mpa is given by h= 146.26 mm (rounded to the nearest hundredth)The max stress can be in tension or compression.

Typos and irrelevant parts of the question should be ignored. Additionally, it is recommended to use the following terms in your answer,  What is stress? Stress is defined as the amount of force acting on a unit area of a material. The stress experienced by a material can be tension, compression, or shear. The bending stress experienced by a beam is an example of a normal stress. It is caused by a load that creates a moment around the beam's neutral axis. What is bending stress? When a beam is loaded by transverse forces, it experiences bending stress. When a beam bends, one side undergoes tension while the other undergoes compression. The maximum bending stress will occur at the point of maximum deflection. Therefore, the bending stress in a beam is a function of the beam's geometry and the magnitude of the load applied. Bending stress in a beam can be calculated using the following equation:σ = (M*y)/Iwhere:σ is the bending stress  M is the bending  is the distance from the neutral axis I is the moment of inertia

learn more about max stress here:

https://brainly.com/question/30899924?

#SPJ4

for a single crystal fcc metal, under uniaxial tension test along its [124] direction, the yield point is 150 mpa. the slip system is (bar{1}11) [101]. calculate the critically resolved shear stress of this particular metal, in units of mpa.

Answers

The critically resolved shear stress of this particular metal, along the (bar{1}11) [101] slip system, is 150 MPa

The critically resolved shear stress (CRSS) is a measure of the amount of stress required to initiate plastic deformation in a crystal along a particular slip system. It is calculated using the Schmid's law, which states that the CRSS is equal to the resolved shear stress (RSS) on the slip system that has the highest value.

The resolved shear stress (RSS) can be calculated using the following formula:

[tex]RSS = \sigma * cos(\theta ) * cos(\lambda )[/tex]

Where:

σ is the applied stress along the loading direction,

θ is the angle between the slip direction and the loading direction, and

λ is the angle between the slip plane and the sample surface normal.

Given:

Yield point (σ) = 150 MPa

Slip system: (bar{1}11) [101]

θ = angle between slip direction and loading direction = 0 degrees (since slip direction [101] is perpendicular to loading direction [124])

λ = angle between slip plane and sample surface normal = 0 degrees (since slip plane is parallel to sample surface)

Plugging in these values into the formula:

[tex]RSS = 150 * sin(0) * cos(0) = 150 * 1 * 1 = 150 MPa[/tex]

Since there is only one slip system given, which is (bar{1}11) [101], the CRSS will be equal to the RSS, which is 150 MPa.

Learn more about critically resolved shear stress

brainly.com/question/19426482

#SPJ4

what does the use of the bracket set and the stepped truss system do in eastern architecture? multiple choice question. it distributes the weight of the roof evenly across a series of columns. it is limited to designs with roofs of only one degree of pitch. it allows for the spanning of vast open spaces. it requires large columns that are able to bear considerable direct weight.

Answers

It is important to carefully read all of the answer choices before selecting the correct one. In this case, the correct answer is "It allows for the spanning of vast open spaces.

"The use of the bracket set and the stepped truss system in Eastern architecture has a specific function. It allows for the spanning of vast open spaces. By distributing the weight of the roof evenly across a series of columns, the bracket set and stepped truss system provide a strong support system that allows for large areas to be covered without the need for additional columns or supports.In addition to its functional purpose, the bracket set and stepped truss system are also important elements of Eastern architecture from an aesthetic perspective. The intricate patterns and designs that are often used in the construction of these systems reflect the rich cultural heritage of the region and the skill of the artisans who create them. Overall, the use of the bracket set and stepped truss system is an important component of Eastern architecture that serves both a functional and an aesthetic purpose.

for more such question on spanning

https://brainly.com/question/28567663

#SPJ11

what kind of warehouse is created to serve customers whether they order in bulk quantities, like full-pallet quantities, or individual items for household delivery?
-All-purpose warehouse -mnipotent warehouse -mni-shore warehouse -mni-channel warehouse Versatile warehouse

Answers

Answer:

The type of warehouse that is created to serve customers who order in both bulk quantities (such as full-pallet quantities) and individual items for household delivery is called a "multi-channel warehouse."

Explanation:

A multi-channel warehouse is designed to accommodate various types of order fulfillment methods, including traditional retail, e-commerce, and wholesale distribution. It allows companies to cater to different customer needs, whether they prefer to purchase in bulk or individual quantities.

This type of warehouse is versatile and can handle various order types, including single-item orders, pallet orders, and even special requests like customized packaging or labeling. The warehouse can also integrate with different sales channels, such as online marketplaces, brick-and-mortar stores, and third-party logistics providers.

what effect, if any, would a change in ambient temperature or air density have on gas turbine engine performance?

Answers

A change in ambient temperature or air density can have a significant effect on gas turbine engine performance. These factors influence the engine's efficiency, power output, and fuel consumption.


1)Firstly, an increase in ambient temperature causes a decrease in air density. As air density decreases, the mass of air entering the engine per unit time (mass flow rate) also decreases. This leads to a reduction in the engine's power output since less air is available for combustion with fuel. Conversely, a decrease in ambient temperature increases air density, resulting in a higher mass flow rate and increased power output.

2)Secondly, a change in ambient temperature affects the engine's thermal efficiency. Higher temperatures cause an increase in the temperature difference between the inlet air and the hot gases exiting the combustion chamber, which can lead to decreased thermal efficiency. Lower ambient temperatures, on the other hand, increase thermal efficiency as the temperature difference is greater.

3)Lastly, variations in air density can also affect fuel consumption. When air density is low, the engine requires more fuel to maintain a specific power output, leading to increased fuel consumption. Conversely, higher air density allows the engine to achieve the desired power output with less fuel, resulting in improved fuel efficiency.

4)In conclusion, changes in ambient temperature and air density significantly impact gas turbine engine performance by influencing power output, thermal efficiency, and fuel consumption. Understanding these effects is crucial for optimal engine operation and management.

For such more question on power output

https://brainly.com/question/29746696

#SPJ11

A 10-cm high and 20-cm wide circuit board houses on its surface 100 closely spaced chips, each generating heat at a rate of 0.08 W and transferring it by convection to the surrounding air at 258C. Heat transfer from the back sur-face of the board is negligible. If the convection heat trans-fer coefficient on the surface of the board is 10 W/m2·8C and radiation heat transfer is negligible, the average surface tem-perature of the chips
(a) 268C (b) 458C (c) 158C(d) 808C (e) 658C

Answers

Note that the average surface temperature of the chips is (a) 268°C.

What is the explanation for the above response?

The total heat generated by the chips is:

Q = 100 chips × 0.08 W/chip = 8 W

The surface area of the circuit board is:

A = 0.1 m × 0.2 m = 0.02 m²

The heat transfer rate by convection is:

q_conv = h × A × (T_s - T_∞)

where h is the convection heat transfer coefficient, T_s is the surface temperature of the board, and T_∞ is the surrounding air temperature.

Rearranging the above equation gives:

T_s = (q_conv / (h × A)) + T_∞

Substituting the given values, we get:

T_s = (8 W / (10 W/m²·°C × 0.02 m²)) + 25°C

T_s = 268°C

Therefore, the average surface temperature of the chips is (a) 268°C.

Learn more about average surface temperature  at:

https://brainly.com/question/5995940

#SPJ1


incompressible steady flow in the inlet between parallel
plates in Fig. P3.17 is uniform, u U0 8 cm/s, while
downstream the flow develops into the parabolic laminar
profile u az(z0 z), where a is a constant. If z0 4 cm
and the fluid is SAE 30 oil at 20°C, what is the value of
u
max in cm/s?

Answers

The maximum velocity (u_max) in the parabolic laminar flow is 12 cm/s.

How to solve

In the problem statement, it is given that the incompressible steady flow is uniform with u = U0 = 8 cm/s in the inlet.

Downstream, the flow develops into a parabolic laminar profile with u = az(z0 - z). The fluid is SAE 30 oil at 20°C, and z0 = 4 cm.

First, we need to find the dynamic viscosity of SAE 30 oil at 20°C. SAE 30 oil has a kinematic viscosity (ν) of approximately 300 cSt (centistokes) at 20°C.

To convert this to dynamic viscosity (μ), we need to multiply by the density (ρ) of the oil:

μ = ν * ρ

The density of SAE 30 oil is approximately 0.89 g/cm³ (890 kg/m³). Since 1 cSt is equal to 1 × 10⁻⁶ m²/s, the kinematic viscosity in SI units is 300 × 10⁻⁶ m²/s.

Now, let's convert the density to SI units:

ρ = 890 kg/m³ = 0.89 g/cm³

Thus, the dynamic viscosity (μ) can be calculated as follows:

μ = (300 × 10⁻⁶ m²/s) * (890 kg/m³) = 0.267 kg/(m*s)

Now, we need to find the maximum velocity (u_max) in the parabolic laminar flow, which occurs at the center of the plates (z = z0/2):

u_max = a * z0/2 * (z0 - z0/2)

Since the flow is incompressible, the mass flow rate (Q) remains constant throughout. We can equate the mass flow rate at the uniform flow (Q_inlet) with the mass flow rate at the parabolic flow (Q_parabolic):

Q_inlet = Q_parabolic

ρ * U0 * A_inlet = ∫[ρ * a * z * (z0 - z) * A_parabolic] dz

The area A_inlet and A_parabolic both can be represented as A = b * z, where b is the width of the parallel plates, and z is the distance between the plates.

Therefore, the equation simplifies to:

U0 * b * z0 = ∫[a * z * (z0 - z) * b] dz, with integration limits 0 to z0

U0 * z0 = ∫[a * z * (z0 - z)] dz, with integration limits 0 to z0

8 cm/s * 4 cm = a * ∫[z * (4 cm - z)] dz, with integration limits 0 to 4 cm

32 cm²/s = a * ∫[4z - z²] dz, with integration limits 0 to 4 cm

Now we can integrate and apply the limits:

32 cm²/s = a * [2z² - (1/3)z³] | (0 to 4 cm)

32 cm²/s = a * [(2 * 4² - (1/3) * 4³) - 0]

32 cm²/s = a * (32 - 64/3)

32 cm²/s = a * (32 - 21.33)

32 cm²/s = a * 10.67 cm²

Now we can solve for 'a':

a = 32 cm²/s / 10.67 cm² = 3 cm/s

Finally, we can find the maximum velocity (u_max) at the center of the plates

Now that we have the value of 'a' (3 cm/s), we can find the maximum velocity (u_max) at the center of the plates (z = z0/2):

u_max = a * z0/2 * (z0 - z0/2)

u_max = 3 cm/s * (4 cm)/2 * (4 cm - 4 cm/2)

u_max = 3 cm/s * 2 cm * 2 cm

u_max = 12 cm/s

Thus, the maximum velocity (u_max) in the parabolic laminar flow is 12 cm/s.

Read more about steady flow here:

https://brainly.com/question/30321558

#SPJ1

for a 1044 steel that is cooled relatively slowly to room temperature, what is the expected weight fraction of cementite in the as-cooled microstructure?

Answers

the expected weight fraction of cementite in the as-cooled microstructure is 0.02.

For a 1044 steel that is cooled relatively slowly to room temperature. What is the 1044 steel? Steel 1044 is a carbon steel with medium carbon content. It is commonly used for bolts, studs, and shafts due to its excellent weldability, strength, and hardness after heat treatment. The steel's physical properties are determined by the cooling rate from high temperatures during its production and processing .A slow cooling rate produces a pearlitic microstructure in 1044 steel, with a weight fraction of cementite (Fe3C) between 0.01 and 0.03. Cementite is formed when carbon molecules join with iron molecules to create a distinct compound, Fe3C. As-cooled microstructures of 1044 steel can be predicted using this data.

learn more about weight fraction here:

https://brainly.com/question/15218448

#SPJ4

meta quest 2 are compatible on ps4 vr starter pack? yes or not​

Answers

Answer: The short answer is: no, No, Oculus Quest 2 is not officially compatible with any Playstation console.

The transfer port on a two-cycle engine directs the air-fuel mixture from the to the BUR two qucle engine

Answers

The air-fuel mixture is directed from the crankcase to the combustion chamber by the transfer port on a two-cycle engine.

The two-cycle engine's entry point for the air-fuel combination?

Compression stroke: The inlet port opens, allowing the air-fuel mixture to enter the chamber and be compressed as the piston rises. The compressed fuel is ignited by a spark plug, starting the power stroke.

Which port does the crankcase to cylinder transmission of compressed air or air-fuel combination take place through?

Transfer Port Through the transfer port, compressed air and fuel are moved from the crankcase to the combustion area. Exhaust Gas Port the exhaust gas port is where exhaust gas exits the combustion area.

To know more about combustion visit:-

https://brainly.com/question/1232655

#SPJ9

Other Questions
the company you valued has an equity value of $890 million. you discover the company has a minority passive stake with a book value of $12 million and a market (price) to book ratio of 3.8 for that industry. the company also has a majority active position with a book value of minority interest of $10.5 million with an industry market (price) to book of 2.2. the initial financial statements were fully consolidated. what should be the new valuation of equity taking into account these holdings? (3 points) which information will be included when the nurse is providing teaching to a client scheduled for a cardiac catheterization via the femoral approach A player kicks a football off the ground so that if travels with a velocity of 32 miles per hour at an angle of 34 with the ground. Find the magnitude of the horizontal and vertical components. which initialization parameter can disable memory advisors and automatic shared memory management? (choose the best answer.) a. control management pack access b. statistics level c. memory target d. memory advisors cannot be disabled. At one college, GPAs are normally distributed with a mean of 2.9 and a standard deviation of 0.6. Find the 70th percentile. What is 2^20002 to the power of 2000Answer in number form. Not scientific notation or e notation. 1 1/9 x 2 2/5 as a mixed number in simplest form what characteristic do all of the outer planets have in common? responses they are small and dense they are small and dense they have liquid cores they have liquid cores they are mostly made of hydrogen and helium they are mostly made of hydrogen and helium they lack moons If Beowulf does not win the battle with Grendel, what does he want done with hisarmor? a eurobond issue is denominated in a particular currency but sold to investors in national capital markets other than the country that issued the denominating currency true false Jeremy and Leslie are each flying their own drones in a flat field with their drones hovering between the two of them. Jeremy's drone is closer to him than to Leslie, and Leslie's drone is closer to her than to Jeremy. Jeremy's drone is 30 meters above the ground, and he is located 50 meters tothe left from the point directly below the drone. The angle of elevation from Leslie's location on the ground to her dronp is 55, and the distance between her location on the ground and her drone is 70 meters.1. Calculate whose drone is higher. Show all work.2. The angle elevation from the lower drone to the higher drone is 25 degrees. Use this information to calculate the distance between Jeremy and Leslie. Show all work.3. Jeremy now flies his drone vertically so that it is the same height as Leslies drone. Draw a new diagram that includes Jeremy, Leslie, and the drones after Jeremy flies his drone to the same height as Leslies.4. Explain why the angle of elevation from Jeremys location on the ground to his drone is different from the angle of elevation between Leslies location on the ground and her drone, given that both drones are at the same elevation above the ground. 5. Calculate the angle of elevation from Jeremys location on the ground to his drone to validate your reasoning. Show all work. 8. A square and its dimensions are shown below. What is the perimeter of the square? Razak's mother weighs, 64.8kg. If she weighs 4 times the weight of Razak, What is Razak's weight? hw11.7. estimate digits estimating the number of correct digits do you know how accurate your solutions are? the ability to print a solution to many digits does not imply that we actually have an answer that is accurate to that precision. for this problem, you must solve a linear system and indicate how many accurate decimal digits there are in your solution. you may use functions from numpy.linalg for this problem. numpy.linalg.solve and numpy.linalg.cond may be particularly useful. if i run the same code several times, sometimes my solution is correct and sometimes it is not. what is going on? one possibility is that you are rounding incorrectly. think about this: if i have 4.9 accurate digits, should i say that five of my digits are accurate, or four of my digits are accurate? you may also be calculating the number of decimal digits for double precision numbers incorrectly (sixteen digits is only an approximation). the setup code gives the following variables: name type description a numpy float64 array matrix b numpy float64 array vector your code snippet should define the following variables: name type description correct digits integer indicates how many meaningful digits there are in x numpy array the that solves user code.py the process by which individuals outside an organization are brought into a beneficial relationship with it, making them dependent on the regime for certain rewards, is known as a. integration. b. co-optation. c. acculturation. d. dependency. I have a question,what is 3x + 2 = 17 It was a very ............. match! England won with 3-2 with a goal in the last minute Ten cards numbered 1 thru 10 are placed in a box. If a card is de random from the box, what is the probability of drawing a prime a 10% b 25% c 40% d 50% I wrote a Pong Project on CodeHs (Python) (turtle) and my code doesn't work can you guys help me:#this part allows for the turtle to draw the paddles, ball, etcimport turtlewidth = 800height = 600#this part will make the tittle screenwn = turtle.Screen()turtle.Screen("Pong Game")wn.setup(width, height)wn.bgcolor("black")wn.tracer(0)#this is the scorescore_a = 0score_b = 0#this is the player 1 paddlepaddle_a = turtle.Turtle()paddle_a.speed(0)paddle_a.shape("square")paddle_a.color("white")paddle_a.shape.size(stretch_wid = 5, stretch_len = 1)paddle_a.penup()paddle_a.goto(-350, 0)#this is the player 2 paddlepaddle_b = turtle.Turtle()paddle_b.speed(0)paddle_b.shape("square")paddle_b.color("white")paddle_b.shapesize(stretch_wid = 5, stretch_len = 1)paddle_b.penup()paddle_b.goto(350, 0)#this is the ballball = turtle.Turtle()ball.speed(0)ball.shape("square")ball.color("white")ball.penup()ball.goto(0, 0)ball.dx = 2 ball.dy = -2#Penpen = turtle.Turtle()pen.speed(0)pen.color("white")pen.penup()pen.hideturtle()pen.goto(0, 260)pen.write("Player A: 0 Player B: 0", align="center", font=("Courier", 24, "normal"))#this is a really important code, this part makes it move players 1 and 2 paddlesdef paddle_a_up(): y = paddle_a.ycor() y += 20 paddle_a.sety(y)def paddle_a_down(): y = paddle_a.ycor() y -= 20 paddle_a.sety(y)def paddle_b_up(): y = paddle_b.ycor() y += 20 paddle_b.sety(y)def paddle_b_down(): y = paddle_b.ycor() y -= 20 paddle_b.sety(y)#these are the controls for the paddleswn.listen()wn.onkeypress(paddle_a_up, "w")wn.onkeypress(paddle_a_down, "s")wn.onkeypress(paddle_b_up, "Up")wn.onkeypress(paddle_b_down, "Down")#this is the main game loopwhile True: wn.update() #this will move the ball ball.setx(ball.xcor() + ball.dx) ball.sety(ball.ycor() + ball.dy) #this is if the ball goes to the the other players score line if ball.ycor() > 290: ball.sety(290) ball.dy *= -1 if ball.ycor() < -290: ball.sety(-290) ball.dy *= -1 if ball.xcor() > 390: ball.goto(0, 0) ball.dx *= -1 score_a += 1 pen.clear() pen.write("Player A: {} Player B: {}".format(score_a, score_b), align="center", font=("Courier", 24, "normal")) if ball.xcor() < -390: ball.goto(0, 0) ball.dx *= -1 score_b += 1 pen.clear() pen.write("Player A: {} Player B: {}".format(score_a, score_b), align="center", font=("Courier", 24, "normal")) # this makes the ball bounce off the paddles if (ball.xcor() > 340 and ball.xcor() < 350) and (ball.ycor() < paddle_b.ycor() + 40 and ball.ycor() > paddle_b.ycor() - 40): ball.setx(340) ball.dx *= -1 if (ball.xcor() < -340 and ball.xcor() > -350) and (ball.ycor() < paddle_a.ycor() + 40 and ball.ycor() > paddle_a.ycor() - 40): ball.setx(-340) ball.dx *= -1 The number of students who ride the school bus is 110%of the number of students who walk.How many students ride the school bus